city of johnson arkansas logo

RESOLUTION 2015-13

RESOLUTION NO. 2015-13
A RESOLUTION AUTHORIZING EXECUTION OF AN
ENGINEERING DESIGN CONTRACT FOR 56th STREET
FROM DON TYSON PARKWAY TO JOHNSON MILL
BOULEVARD
WHEREAS, the Cities of Springdale and Johnson have received STP-A funding
for up to 80% of cost of design for the 56 St widening/construction from Don Tyson
Parkway to Johnson Mill Boulevard,
WHEREAS, using the procurement procedures required by State law, the
program management team has selected the most qualified firm and has negotiated
design fees with Engineering Services, Inc. in the not to exceed amount of $503,549.63.
WHEREAS, the City of Springdale is responsible for 70% of the 20% local
match (14% of the total design costs) and the City of Johnson is responsible for 30% of
the 20% local match, (6% of total design costs):
Funding Source
Federal Aid
City of Springdale
City of Johnson
Project Totals
Percent Share
80%
14%
6%
100%
Cost Share
$ 402,839.70
$70,496.95
$ 30,212.98
$ 503,549.63
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
JOHNSON, ARKANSAS, that the Mayor and Recorder-Treasurer are hereby
authorized to execute a contract with Engineering Services, Inc. not to exceed amount
of $503,549.63 to move forward with the design phase of this project.